CITY of RAPID CITY

Agenda Item Summary

 

Public Works Committee Meeting Date: 1/12/2016

City Council Meeting Date: 1/19/2016

Staff Contact: Klare Schroeder

Petitioner: Click here to enter text.

Location:

 

Agenda Title:

Change Order No. 1F to Stanley J Johnsen Concrete Contractor for Concrete Panel Repair – West Chicago & Corral Drive, Project No. 13-2131 / CIP No. 50445, for an increase of $6,405.50.

 

 

Summary:

Increase to contract based on actual quantities installed.

Funding Source & Fiscal Impact (if applicable):

 

Fund

Cost Center

 

Fund

Cost Center

General

STCM

 

CIP

Streets

 

 

 

 

 

 

 

 

 

 

 

x

Budgeted

 

 

Not Budgeted

Recommendation:

Action: Approve

Notes:

City Council Options:

 

Attachments & Links:

Change Order

 

 

 

 

 

Click here to enter text.

Click here to enter text.

Click here to enter text.